Solar Photovoltaic Plant Almansol (Almansa)
The Almansol Solar plant, also known as Almansa solar plant or Almansol I, is located between the towns of Almansa and Bonete, in the province of Albacete. Together with the photovoltaic plants Bonete II, Bonete III, Bonete IV and Campanario I, it is part of a complex of more than 1000 ha of photovoltaic modules combined (more than 220 MWp of combined power).
The solar plant is located in the city of Almansa, in Albacete (Castilla La Mancha), and is accessed through existing access roads that connect to the national road N-330 between Almansa and Bonete.
The Almansol I installation was promoted by Grupotec SPV 3, S.L., which applied for a building permit to construct the plant, as well as a 30/132 kV transformer substation and a 1,990 m long underground evacuation line to the REE connection node in Campanario (132/400 kV).
Ownership & Management
Current Owner
••••••
Market Subject
••••••
Grid Codes
UPP Code
••••••
UOF Code
••••••
UF Code
••••••
REE Connection Node
••••••
Detailed Location
Latitude
••••••
Longitude
••••••
Google Maps
••••••
Installation Type
••••••
Technical Specifications
Power
-
REE Access
42 MW
-
Installed
49.98 MW
Infrastructure
-
Surface Area
100 ha
-
Location
Albacete
Technology
Modules
••••••
Power per Module
••••••
Panel Configuration
••••••
Inverters
••••••
Configuration
Fixed Structure
Electrical Details
-
Max Vdc Voltage
Unknown
-
Output Vac Voltage
630 V
Connection Infrastructure
Substation
••••••
Additional Information
Panel Type
••••••
Commissioning
••••••
REE Connection / Evacuation Voltage
30kV
Additional Notes
Sin seguidores. Estructura fija, anclaje acero e inclinacion a 20º sobre horizontal
Financial Information & References
Estimated CAPEX
••••••
Reference Links
••••••
Recent Performance
Performance Ratio (PR)
••••••
+2.1% vs previous month
Energy
••••••
Annual accumulated: 14.5 GWh
Estimated Revenue
••••••
Average price: 52.4 €/MWh
Capacity Factor
••••••
Zone average: 19.5%
Annualized ROI
••••••
Annualized (P48)
Payback Period
••••••
Based on estimated CAPEX
Revenue / MWp
••••••
Financial efficiency
Average Energy Price
••••••
Last month
Location
Information
Publication date
Thursday, October 16th, 2025