Solar Photovoltaic Plant Escatrón 2
The implementation area of the “Escatrón Solar Dos” photovoltaic plant is located 4.2 km from the municipality of Escatrón, in the Comarca Ribera Baja del Ebro, in the province of Zaragoza. It was commissioned in 2019, and the owner of the plant is Escatrón Solar Dos S.L., which is currently 100% owned by the Everwood capital fund. The initial promoter of the plant was the COBRA Group, which was also responsible for the construction of other photovoltaic plants in the area.
Access to the site is via the regional road A-221, which connects Escatrón with Caspe, and from there via rural roads that provide access to the plots.
The location of the photovoltaic installation was carried out on a set of plots from various polygons, all belonging to the municipality of Escatrón, adjacent to each other and totaling an approximate area of 148.96 hectares, whose prior use and classification was agricultural. Specifically, approximately 134.86 hectares are cataloged as arable land and were therefore used for the project.
The plant connects to Red Eléctrica de España at the node of the 400 kV ARAGON electrical transport substation, located in the municipality of Castelnou (Teruel). To raise the voltage, the plant uses the 30/132/400 kV SUR collector substation, which also serves 6 other photovoltaic plants in the area.
Ownership & Management
Current Owner
••••••
Market Subject
••••••
Grid Codes
UPP Code
••••••
UOF Code
••••••
UF Code
••••••
REE Connection Node
••••••
Detailed Location
Latitude
••••••
Longitude
••••••
Google Maps
••••••
Installation Type
••••••
Technical Specifications
Power
-
REE Access
38 MW
-
Installed
49.85 MW
Infrastructure
-
Surface Area
134.85 ha
-
Location
Zaragoza
Technology
Modules
••••••
Power per Module
••••••
Panel Configuration
••••••
Inverters
••••••
Configuration
With Trackers
Electrical Details
-
Max Vdc Voltage
Unknown
-
Output Vac Voltage
Unknown
Connection Infrastructure
Substation
••••••
Additional Information
Panel Type
••••••
Commissioning
••••••
REE Connection / Evacuation Voltage
30kV
Additional Notes
1.481 Seguidores solares de un solo eje
Financial Information & References
Estimated CAPEX
••••••
Reference Links
••••••
Recent Performance
Performance Ratio (PR)
••••••
+2.1% vs previous month
Energy
••••••
Annual accumulated: 14.5 GWh
Estimated Revenue
••••••
Average price: 52.4 €/MWh
Capacity Factor
••••••
Zone average: 19.5%
Annualized ROI
••••••
Annualized (P48)
Payback Period
••••••
Based on estimated CAPEX
Revenue / MWp
••••••
Financial efficiency
Average Energy Price
••••••
Last month
Other solar plants in Zaragoza
View full mapLocation
Information
Publication date
Thursday, October 16th, 2025